Skip to content

T4-SI-PRO-001

One controlled sequence, every assignment

The same seven steps run on a single valve and on a full fabrication package. The sequence is what makes the evidence comparable across suppliers and across orders.

01Before travel

Intake, risk map and coordination

Scope, standards, acceptance criteria and deliverables are confirmed in writing. Degradation mechanisms and criticality drive where the hold, witness and review points land. Supplier notification, access, schedule and equipment readiness are verified before an inspector leaves.

02On site

Witness and field alert

Inspection is performed under controlled conditions against defined acceptance criteria. Anything affecting schedule, cost or conformity is raised the same day, with the clause it is measured against and the evidence collected at the point of the finding.

03After

Report and closeout

A controlled deliverable carries evidence, revision status and an identified authorizing signature. Release readiness is recommended, nonconformance and corrective action reports are tracked to closure, and records stay retrievable.

R1Route

Inspection points along the manufacturing route

A sample route showing where hold, witness, review and monitoring points typically fall. Actual points are defined by the applicable project ITP.

  1. 01RRaw materialComplete
  2. 02MForgingComplete
  3. 03WHeat treatmentComplete
  4. 04WMechanical testingComplete
  5. 05WNDTCurrent
  6. 06MMachiningPlanned
  7. 07HFinal inspectionPlanned
  8. 08RDocumentationPlanned
  9. 09HReleasePlanned
HHold
Activity is subject to the applicable ITP hold requirements.
WWitness
The inspection party is notified and may witness as defined by the ITP.
RReview
Documentation or evidence is reviewed.
MMonitoring
Manufacturing or inspection activity is monitored as applicable.

Final definitions and attendance requirements are governed by the applicable project ITP and contractual requirements.

R2Notification

Notification of inspection

T4-NOI-SAMPLE

Notification of inspection

Customer
U.S. Equipment Manufacturer
Supplier
Qualified Manufacturing Facility — Northern Mexico
Project
North America Manufacturing Program
Purchase order
PO-XXXXXX
Component
Critical Forged Component
Quantity
6 pcs
Inspection activity
UT witnessing / mechanical test witnessing
ITP reference
ITP-SAMPLE Rev. 2 — steps 070, 080
Planned date
Week 14 — sample
Witness classification
W — Witness